page-template,page-template-full_width,page-template-full_width-php,page,page-id-15634,bridge-core-2.6.3,qode-page-transition-enabled,ajax_fade,page_not_loaded,,qode-title-hidden,qode-theme-ver-24.8,qode-theme-bridge,qode_header_in_grid,wpb-js-composer js-comp-ver-6.5.0,vc_responsive,elementor-default,elementor-kit-15965

CIVIL ENGINEERING AND PROJECT MANAGEMENT CONSULTANT EXPERIENCE

CONTRACT ADMINISTRATION AND INSPECTION SERVICES

on Contracts undertaken by ConsultCivil Pty Ltd since inception:

Ross River Dam to Douglas Water Treatment Plant Pipeline Duplication (Packages 1 & 2, $70M) for TCC, Full Contract Administration Services, providing Superintendent and Superintendent Representative services (April 2023 to July 2024)

Jensen Landfill Rehabilitation ($19M) for TCC, CQA and site inspection services (Stage 1 – 2023, Stage 2 – 2024)

Sewage Pump Station Pipework and Isolation Valve Renewal Contracts for TCC, Site Inspection services (January to June 2024)

Nelly Bay Marina Maintenance Dredging Supervision for TCC (August 2023) inspection services (April to August 2023)

Hervey Range Waste Facility Drop Structure Replacement for TCC, CQA and site inspection services (April to August 2023)

Townsville Ring Road Stage 5 Contract ($280M) for DTMR as Construction Verifier, led a surveillance and verification team of 10 personnel (Project Engineers/Site Inspectors/Environmental Officer) (May 2021 to March 2023)

Hervey Range Slope Stabilisation Works for TMR (2020/Early 2021)

Horseshoe Bay Wastewater Treatment Plant Odour Control Unit (2020/Early 2021) including site inspector

Hervey Range Landfill Cell A & Stage C Capping (2020) including site inspector

Stuart Landfill Cell 3A Interface Liner and Basal Cell Works (2020) including site inspector

Townsville Pistol Club Flood Recovery Works (2020) including design and project management services

North Ward Pump Station 7A and Gravity Sewer Works (2019/Early 2020) including site inspector

Stuart Landfill Cell 2C Interface Liner Project (2019) including site inspector

Cleveland Bay Purification Plant Process Upgrade Project, $65M valve, as Superintendent and Client Project Manager (late 2017 to late 2019)

Employers Representative role for Cape Flattery Silica Mines for Ship Loader Replacement and Reclaimer Refurbishment (Early 2016 to Mid 2018)

Picnic Bay Landfill Closure Works (2018) including site inspector

Jensen Landfill Leachate Extraction & Conveyance Works (2018/Early 2019) including site inspector

L1C Sewerage Pump Station, Rising Main & Gravity Main (2018/Early 2019) including site inspector

Condon Treatment Plant Subnatant Pump Well & Associated Pipework (2018)

Sewer and Manhole Relining Contracts (2017/2018) including site inspector

Wattle Street Footpath Project Management Services, Hinchinbrook Shire Council, Forrest Beach (2017)

Hervey Range Landfill Leachate Extraction & Conveyance Works (2017) including site inspector

Rising Main Duplication Pump Station 7A to Pump Station 7B, HDD Trenchless Installation, (2017) including site inspector

Kirwan Sewer Relining 2016/17 Contract (2016/2017) including site inspector

Townsville Northern Intersection Access Upgrades, Veales to Pope Roads, DTMR Northern (as Administrator Representative) (2016/2017)

Alfred Street Sewerage Pump Station, Rising Main and Gravity Sewer (2016/2017) including Site Inspector

Kitty Creek & Carey Creek Overtaking Lanes, DTMR Mackay (as Administrator) (2016)

Pump Station W4A Redirection Rising Main (2015/2016) including Site Inspector

Charters Towers Road Water Main Replacement (2015) including site inspector

Jensen Landfill Capital Works (2015) including site inspector

Burdell Street Water Main Replacement (as Superintendent) (2015) including site inspector

Francis Street Water Main (as Superintendent) (2015) including site inspector

Percy Street and Toolakea Beach Road Water Main Replacements (2015) including site inspector

Kulburn Booster Pump Station (2015) as Superintendent plus Site Inspector

Pump Station BU07 Rising Main Duplication (2015) as Superintendent plus site inspector

Mount Louisa South Water Main Duplication (2015) as Superintendent

Horseshoe Bay Water Main Replacement (2015) as Superintendent

Pump Station LA16A conversion, site inspections (2015)

Mount Louisa Reservoir #3 Construction, Townsville (2014/2015), including site inspector

Western Outfall Pressure Main Three Creek Pipeline Replacements (2014/2015) including site inspector

Rising Mains for Pump Stations 9F and K21, Townsville (2014/2015), including site inspector

S21 Southern Suburbs Diversion Pump Station and Pressure Main, Townsville (2014/2015), engineering assistance and provision of site inspector

Castle Hill Water Main Replacement, Townsville (2014), including site inspector

Sewer Relining Stage 1, Townsville (2014), including site inspector

Stuart Landfill Interface Liner Stage 1, Townsville (2014) as Superintendent

Stuart Drive Water Main Augmentation, Townsville (2014), including site inspector

Stuart Landfill Capping Stage 1, Townsville (2013/2014) as Superintendent

Hervey Range Landfill Capping Stage A, Townsville (2013/2014) as Superintendent

Hinchinbrook NDRRA Package 4 Multiple Roads Contract, Ingham area (2013/2014)

Corbett Street Trunk Sewer Extension, Townsville (2013/2014), including site inspector

Wulguru Reservoir Upgrade, Townsville (2013)

DESIGN, PROJECT MANAGEMENT AND ENGINEERING SERVICES

undertaken by ConsultCivil Pty Ltd since inception:

Cleveland Bay Purification Plant (CBPP) Recycled Water Treatment Facility for Townsville City Council (TCC), Commissioning Owners Engineer Services (February to June 2024)

Project Management of Project Delivery Phase for Field Lighting Upgrades for Hermit Park Tigers FC and Curra Swans FC AFL ovals (July 2023 to April 2024)

Project Management of Due Diligence Concept Design Phase and Project Delivery Phase for AFL Clubroom Upgrades for Hermit Park Tigers FC and Curra Swans FC (Late 2022 to August 2024)

Set-up and review of Technical Specifications and Tender documentation for Townsville City Council $65M Cleveland Bay Purification Plant Upgrade (2016)

Provide tender and project assistance to local civil contractors and consultants – programming and tender / bid documentation plus Form 16 construction inspections (2014 to present)

Procurement Services for Rockfield Technologies and Cape Flattery Silica Mines for Ship Loader and Reclaimer Replacement (2014 / 2015)

Kin Kora Intersection Upgrade, Constructability Review for Department of Transport and Main Roads, Dawson Highway, Gladstone (2014)

Project Manager for initial stages of the Southern Suburbs Diversion Pump Station and Pressure Main project for Townsville City Council (2013 to Early 2014)

Acting Manager of the Project & Asset Management Services Group within Townsville City Council Engineering Services section (June to Sept 2013)

Asset Engineering for Townsville City Council stormwater drainage and pathway reconstruction programs (2013)

Inspections and Form 16 certifications for Civil Contractors (2015)